Two reinforced concrete bases for a swim spa and hot tub in Sinton Green, plus around 120m² of new paving laid to designed falls with a gradual ramp.

Our client in Sinton Green was preparing his garden for a new swim spa and hot tub, and needed solid bases for both, followed by a new paved area around them. In the first phase we dug out and poured two reinforced concrete bases, measuring 6.5m x 2.5m and 2.4m x 2.4m, each with 200mm of compacted hardcore and 150mm of C30 concrete. In the second phase we paved around 120m² of the garden, including the area around the garden room. Rather than adding steps and retaining walls to deal with the changing levels, we formed the paving with designed falls and a gradual ramp, then finished the scheme with a sleeper border and steps.




The garden had different levels and falls across it, and the client was about to have a swim spa and hot tub installed. Both are extremely heavy once filled, so they needed bases that would not crack or settle, and the ground around them needed a hard surface that would drain properly.
The client wanted a usable garden that linked the swim spa, hot tub and garden room together, without breaking the space up with lots of steps and walls. He also had a particular style of paving slab in mind for the finished area.
For the bases, we specified a full dig-out to 350mm, 200mm of compacted hardcore, rebar mesh throughout and 150mm of C30 concrete, formed within timber perimeter shuttering. Both bases were set slightly raised from ground level.
For the paving, we designed the levels around carefully set falls and a gradual ramp instead of introducing steps or extra retaining walls. This gives a smoother transition between the different levels while keeping water draining off the surface. The slabs were laid on a full sand and cement mortar bed over a compacted hardcore sub-base.


Leave your details and we'll arrange a time that fits your schedule!
Prefer to talk? Call or text us.
The concrete bases were completed in September. Our team excavated both areas, compacted the hardcore, set the shuttering and rebar and poured the concrete, and the digger and skip were collected once the pour was done. The shuttering was struck a few days later, once the concrete had gone off.
The paving phase followed in October and was completed at the end of the month. The full area was excavated, the hardcore sub-base installed and compacted, and the slabs laid to the designed falls and ramp. A sleeper border and steps were added around the property during this phase, and the edges were finished to complete the project.
The client now has two solid, reinforced bases for the swim spa and hot tub, set within around 120m² of new paving that flows across the garden without awkward changes in level. He told us he was very happy with the result, especially once the edges were finished.
With the groundwork done properly, the garden is ready for the swim spa and hot tub, and the paving and sleeper details give the space a finished, cohesive look that will last for years.