Greenhouse Base Installation in the Cotswolds

A two-day reinforced concrete greenhouse base in the Cotswolds, built over prepared clay ground with reclaimed brick detailing and a gravel access area.

Project Overview

Our client in the Cotswolds wanted a solid, long-lasting base for a new greenhouse. The ground in that part of the garden was clay, which moves as it wets and dries and can crack an unprepared slab, so the base needed more than a standard pour. We dug out the area, carried out additional ground preparation and laid a compacted hardcore sub-base before pouring a reinforced concrete slab within timber shuttering. Once the concrete had gone off, we struck the shuttering, laid reclaimed brick detailing around the base and installed a gravelled access area. The work took two days on site, leaving our client with a level, stable platform ready for the greenhouse.

The Problem

The client had chosen a spot for a new greenhouse, but the ground there was clay. Clay holds water in winter and shrinks in dry spells, and a slab laid straight onto it is likely to move, crack or drop out of level over time. For a greenhouse, where the frame and glazing rely on a square, level base, that movement is a real problem.

The client wanted a base that would stay stable for the life of the greenhouse and look right in the garden, rather than a bare concrete pad. Clean, easy access to the greenhouse was also part of the brief.

Our Solution

We designed a reinforced concrete base with additional ground preparation to deal with the clay. The area was excavated and a compacted hardcore sub-base laid to spread the load and give the slab a firm bed. Steel rebar was set within the slab to help it resist cracking if the ground moves.

To soften the edge of the base and tie it into the garden, we specified reclaimed brick detailing around the perimeter. A gravelled access area was added in front of the greenhouse, giving a clean, practical surface to walk on in all weathers without the mud that comes with clay soil.

Contact us today

BOOK YOUR DESIGN VISIT

Leave your details and we'll arrange a time that fits your schedule!

Prefer to talk? Call or text us.

Thanks for reaching out, we'll be in touch very soon!
Oops! Something went wrong while submitting the form.

Project Execution

The first stage covered the dig-out, ground preparation and sub-base. The hardcore was compacted with a wacker plate, timber shuttering was set square and level, and the rebar was positioned before the concrete was poured and levelled. Spoil was taken away in a skip.

With the concrete cured, we returned to strike the shuttering, lay the reclaimed brick detailing and install the gravel access area. The work took two days on site in total, split either side of the curing period.

Results

Our client now has a level, reinforced base ready for the greenhouse, built to cope with the movement of the clay beneath it. The reclaimed brick edge gives the base a finished look that sits comfortably in a Cotswold garden.

The gravel access area means the greenhouse can be reached easily all year round, and the base will give the frame and glazing a stable footing for many years to come.

Landscaping Guides

How Much Does Composite Fencing Cost Per Metre

Composite fencing typically runs £120 to £250 per metre installed, with ground, access and board quality driving the spread. Plex Group explains what moves the figure.

Why Are Stones Coming Loose From My Resin Driveway

Loose stones on a resin driveway are ravelling, an installation failure rather than wear. Plex Group explains the causes and the repair across Worcestershire and Warwickshire.

Why Do My Fence Panels Keep Blowing Out In The Wind

Fence panels blow out because solid panels catch wind, fixings are weak or the posts had already failed. Plex Group explains the causes and the proper fix across Worcestershire and Gloucestershire.